Energy saving refrigeration solution supplier since 2004.                                                                                                                                                                                                                                                                                                   

Language

Case Study: 2-Ton Sausage Quick-Freezing Tunnel in Zhangzhou

This case study highlights a successful project involving the installation and commissioning of a 2-ton sausage quick-freezing tunnel in Zhangzhou, demonstrating CBFI's comprehensive services in design, manufacturing, installation guidance, training, and on-site testing.

Project Overview

The project commenced with a detailed design phase, where CBFI engineers collaborated closely with the client to customize the quick-freezing tunnel to meet their specific requirements. This proactive approach ensured optimal performance and efficiency.


Installation Process

The installation involved multiple critical stages:


Base Plate Installation: CBFI's team meticulously prepared the foundation, ensuring stability and alignment for the subsequent components.



Tunnel Frame Welding: Skilled engineers conducted the welding of the tunnel frame, ensuring structural integrity and durability.



Evaporator Installation: The installation of the evaporator was executed with precision, as it plays a vital role in the quick-freezing process.



Main Unit Setup: CBFI ensured the main unit was installed correctly, guaranteeing seamless operation.



Evaporative Cooling Installation: The evaporative cooling system was integrated to enhance the freezing efficiency of the tunnel.



Shelf Installation: The installation of shelves was crucial for maximizing space and efficiency within the freezing tunnel.



Mesh Belt Installation: Finally, the mesh belt was installed, enabling smooth transportation of sausages through the freezing process.



On-Site Testing and Training

Following the installation, CBFI engineers conducted on-site testing of the machinery. This crucial step ensured that all components functioned harmoniously, meeting the operational standards expected by the client. The team also provided comprehensive training to the client’s staff, equipping them with the knowledge and skills necessary for efficient machine operation and maintenance.



Client Production Trials

The project culminated in successful production trials, showcasing the system's capabilities. CBFI’s engineers were present to oversee the process, offering guidance and addressing any challenges that arose, further exemplifying CBFI's commitment to customer satisfaction.



Conclusion

This 2-ton sausage quick-freezing tunnel project in Zhangzhou illustrates CBFI's dedication to providing end-to-end solutions, from design and manufacturing to installation and training. Our focus on quality and customer support ensures that clients receive not only advanced technology but also the expertise needed to maximize their investment in our machinery.


Basic Information
  • Year Established
    --
  • Business Type
    --
  • Country / Region
    --
  • Main Industry
    --
  • Main Products
    --
  • Enterprise Legal Person
    --
  • Total Employees
    --
  • Annual Output Value
    --
  • Export Market
    --
  • Cooperated Customers
    --

Recommended

Send your inquiry

Send your inquiry

Choose a different language
العربية
English
Español
français
Polski
Português
русский
Türkçe
Current language:English