The project is under construction phase 2 to do the floor treatment. January 15, 2019.
The bottom layer of the floor is cement. Waterproof paint layer is the second one. And a waterproof film is put on. Then extruded sheet is used for insulation. Steel wire net is used for structure support. And a new cement layer is put on the top.